Chief Executive at a energy/utilities company with 1-10 employees
Real User
Top 20
2024-11-12T19:52:53Z
Nov 12, 2024
Our primary use case for Oracle Primavera Portfolio Management was during a period when we deployed it for five or six years. We were actively using it without any other tools. It was mainly for managing projects, specifically in the construction and installation phases of instrumentation and controls.
I am an end user of Primavera, not a developer. I am a project planner, and Primavera is a tool I use as a project planner. We use it for specific major projects where the client specifies that they need Primavera.
I think Oracle Primavera Portfolio Management is a well-engineered product from an IT perspective. With the product's user interface and from an end user's perspective, it is a very complicated tool, especially for those in the early stages of their profession involved in project management.
I work for an engineering and construction company that uses Primavera for project planning and management. We use it in specific projects when clients request it.
Project Portfolio Management (PPM) encompasses processes and tools that help an organization manage its projects to align with strategic objectives, prioritize resources, and ensure effective execution.PPM tools support businesses in evaluating potential projects and tracking ongoing project performance. They enable decision-makers to allocate resources effectively, ensuring alignment with corporate goals. By providing a centralized view, PPM systems streamline project selection, planning,...
Our primary use case for Oracle Primavera Portfolio Management was during a period when we deployed it for five or six years. We were actively using it without any other tools. It was mainly for managing projects, specifically in the construction and installation phases of instrumentation and controls.
I am an end user of Primavera, not a developer. I am a project planner, and Primavera is a tool I use as a project planner. We use it for specific major projects where the client specifies that they need Primavera.
I think Oracle Primavera Portfolio Management is a well-engineered product from an IT perspective. With the product's user interface and from an end user's perspective, it is a very complicated tool, especially for those in the early stages of their profession involved in project management.
I work for an engineering and construction company that uses Primavera for project planning and management. We use it in specific projects when clients request it.
Oracle Primavera Portfolio Management is used for projects.
We use the solution for portfolio management, including engineering document management for mega projects.